We are Team 13. We are continuing the project started by Team 15. This is based on their original site.
Resources
Updated Documentation
- Requirements Specification
- Architecture
- Method Selection and Planning
- Risk Assessment
- Implementation
- Testing:
- Continuous integration
- Code Documentation
Game Files
Sprint Updates - Team 13
19/01 - 25/01
General plan for the project discussed. Figured out new requirements (not many were needed). Implemented powerups. Implementation was slightly delayed as some extra refactoring was needed to get powerups to work. Hence we did not start the work on difficulty or CI.
26/01 - 01/02
Finalized the strategy for change management. Added difficulty (with a special screen to select difficulty). Started researching CI and even some testing. Started implementing saving by first implementing a pause screen. Finished implementing saves. Wrote some “test” tests. CI research still ongoing, but getting quite close to implementing it.
23/01 - 09/02
Put CI in place. Writing tests and reports, prioritizing new feature tests and those that can be linked to a requirement. . Produced a concrete architecture from now finished implementation.
09/02 - 10/02
Final Checks, making sure everything is up to date and getting ready to submit.
Sprint Updates - Team 15
15/10 - 22/10
This week we were slightly delayed getting the requirements written-up however we do not expect to go past the 28/10 complete date for these tasks.
23/10 - 29/10
The requirements were completed by 29/10 which keeps us on track as planned. We have a breakdown of each task that needs to be completed and have planned accordingly. We have also discussed which methods and tools we will be using; this is yet to be written up however. Furthermore, we decided to start doing a Risk Assessment this week; sooner than anticipated in case the risks arise earlier.
30/10 - 05/11
Having gotten a diagram for the Abstract Architecture completed, we started implementing as soon as possible as it appears writing about the Architecture is going to take us longer than expected. We’ve also completed the Risk Assessment and are in good place to identify and mitigate risks should they arise.
06/11 - 12/11
We have discussed our method and tool selection and have documented our Abstract and Concrete Architecture representations - though these need to be related to the requirements yet.
13/11 - 19/11
We have completed our representation of the Concrete Architecture as the Implementation is well under way; no changes to the Architecture of the game will be changed at this point. We are yet to discuss unimplemented requirements but that should be done over the weekend.
19/11 - 25/11
All the deliverables have been completed and submitted.